Buyer guide

Rig moving and heavy-haul planning basics

Start with a complete load list from the rig owner, then settle route, permits, escorts, lifting and timing before you compare haulers. A rig move works when one party coordinates the sequence and every handoff is written down. Quotes only compare when they cover the same loads and the same assumptions.

Define the move and build the load list

A rig move is a series of loads between two locations, and the quote depends on what is in each load. Ask the rig owner for a load list that gives each piece, its weight and its overall dimensions. Without it, a hauler must guess at trailer type, number of trucks and permit class, and every guess ends up priced in.

Decide early whether you are buying a rig move, a heavy haul or both. A rig move usually covers the whole package of trailers, trucks and crews for one rig. A heavy haul covers a single oversize or overweight load, such as a vessel or module. The scope of work, the permits and the party in charge differ, so name the job plainly in the enquiry.

  • Rig floor, substructure, mast or derrick and drawworks components, each listed as a separate load.
  • Mud tanks, pumps, power units, boilers and accommodation trailers.
  • Whether the rig is laid down, partly rigged down or moved with parts attached.
  • Matting, camp units, light plants and loose equipment that travel with the rig.
  • Any item that exceeds normal road dimensions or weight and needs special trailers.

Route, permits and who holds them

Oversize and overweight loads travel on routes approved by the road authority, and a route that suits the load may be longer than the shortest drive. Ask whether the hauler surveys the route, applies for permits and absorbs the lead time. Confirm current permit and escort requirements with Alberta Transportation and Economic Corridors or the road authority that covers your route.

Lease and access roads often fall to the operator or the lease builder. Bridges, culverts, overhead lines, tight turns and soft ground can all change the plan. Settle early who walks the final approach and who corrects problems found on the day.

Ask the hauler how it prices a route that changes after the permit is issued. A detour, a closed crossing or a bridge that cannot carry the load can add distance and time. Agree in advance who approves the change, who pays for a revised permit and how the new route is communicated to drivers and escorts.

Road bans, seasons and timing

Many regions restrict heavy loads on some roads during spring thaw and wet periods, and frozen ground in winter can open access that is closed in summer. Confirm current restrictions with the road authority before you fix a date. Ask each hauler how it prices a move that slips because of weather, a ban or a late rig release.

Weather can stop a move after trucks and crews are already committed. Ask what the hauler charges when loads are staged but cannot travel, whether crews are held on site or released, and how the move is rescheduled. A supplier with a clear weather and ban policy is easier to plan around than one that answers case by case.

  • The earliest and latest dates you can accept for rig release and spud.
  • Whether the lease can take the load in its current condition or needs matting.
  • Whether daylight or traffic windows limit when oversize loads may travel.

Pilot vehicles, cranes and pickers

Escorts, lifting equipment and labour sit around the haul itself, and quotes often leave them out. Ask whether pilot vehicles are included, how many the route needs, and who supplies the crane or picker at each end. A picker places smaller loads on the lease. A crane handles heavier lifts such as the mast or substructure.

Pin down the lifting plan with the party who owns the lift. Confirm the lifting equipment, rigging and operators are supplied by the party you expect, and that the lift is planned with the lease layout in mind. Ask who is responsible if the lift needs more capacity than expected.

Who usually decides or supplies each part of a rig move
ItemUsually decided or supplied byWhat to confirm
Load list and weightsRig ownerComplete, current and issued before quotes
Route survey and permitsHauler or a permit serviceWho applies, who pays, and who carries the lead time
Pilot or escort vehiclesHauler or a separate escort supplierWhether the route needs them and who is billed
Crane or picker at each endHauler, operator or lifting contractorCapacity, rigging, operator and standby terms
Lease and access readinessOperator or lease builderSurface condition, matting and final approach
Overall sequence and handoffsOperator representative or rig ownerOne named coordinator with authority to change the plan

Rig-out and rig-in sequence and who coordinates

Rig-out is releasing and loading at the old location. Rig-in is unloading and setting up at the new one. The two ends must stay in step, because trucks that wait at either end are billed. Write down the order in which loads leave and arrive, and what happens if one piece is not ready.

Name the coordinator. It may be an operator representative, the rig owner or the hauler, but it must be one person with authority on the day. Ask how standby, short-notice changes and a failed lift are handled, and who signs the daily tickets.

Compare haul quotes and confirm before award

Compare quotes against the same load list and the same assumptions about permits, escorts and lifts. Ask whether the price is per load, per truck, per hour or for the whole move, and what minimums and standby terms apply. Check insurance, driver qualifications and equipment availability for your window against your own prequalification before you award.

Look at what the quote leaves out. Common gaps are escorts, lifting, matting, camp or accommodation for crews, return of empty trailers and clean-up after the move. Ask each hauler to mark every item as included, excluded or billed at cost, so the comparison shows the full scope of work and not only the trucking.

How quotes end up not comparable

  • Requesting quotes without a load list, so each hauler assumes a different set of loads.
  • Leaving permits, escorts and lifting out of the scope and finding them on the invoice.
  • Fixing a date before checking road restrictions and lease condition.
  • Treating the two ends of the move as separate jobs with no single coordinator.
  • Comparing a per-load price with a per-hour price as if they were the same thing.

This guide is general buying guidance for a conversation with a provider. It is not engineering, legal or safety advice. Confirm current regulatory requirements with the regulator for your province.